2018, HPP Malczyce, the Odra River, Poland

Implementation details

Project name:
Supply, installation and initiation of the NEPTUN fish behaviour management system on the upper and lower water of the HPP Malczyce, the Odra River in Malczyce

Location:
Odra River, Malczyce, Poland

Date:
December 2018

Aim:
Fish protection against entering to the hydro power plant turbines and directing to the fish pass.

Installation parameters – Upper Water- Type: NEPTUN

  • Barrier length: 84 m
  • Electrodes lengt: 6,5 m
  • Electrodes mounting: to the bottom
  • Power supply: 3-phase

Installation parameters – Lower Water – Type: NEPTUN

  • Barrier length: 71 m
  • Electrodes lengt: 6,5 m
  • Electrodes mounting: to the bottom
  • Power supply: 3-phase