2018, HPP Malczyce, the Odra River, Poland
Implementation details
Project name:
Supply, installation and initiation of the NEPTUN fish behaviour management system on the upper and lower water of the HPP Malczyce, the Odra River in Malczyce
Location:
Odra River, Malczyce, Poland
Date:
December 2018
Aim:
Fish protection against entering to the hydro power plant turbines and directing to the fish pass.
Installation parameters – Upper Water- Type: NEPTUN
- Barrier length: 84 m
- Electrodes lengt: 6,5 m
- Electrodes mounting: to the bottom
- Power supply: 3-phase
Installation parameters – Lower Water – Type: NEPTUN
- Barrier length: 71 m
- Electrodes lengt: 6,5 m
- Electrodes mounting: to the bottom
- Power supply: 3-phase